River Nyamwamba Flood Mitigation Against Damage - Kasese
Main Components and Physical sizes
Emergency Maintenance of River Nyamwamba for Flood Mitigation Against Damage of Critical Infrastructure and Loss of Livelihoods.
SCOPE OF WORKS:
- River Nyamwamba - Desilting/Dredging/Excavation and Breaking up Boulders within water channel.
- Construction of River side bunds/Embankment by filling excavated material and boulders.
- Protect River embankment by PVC coated gabions.
- Protect River embankment by Cyclopean concrete at Curves/Critical areas.
PHYSICAL SIZE OF WORKS:
- Excavation/Dredging and Boulder breaking – 168,599m3
- Construction of River bunds/Embankment – 149,000m3
- Gabion protections – 7,660m3
- Cyclopean Concrete works – 8,141m3